OPERATIONS MANAGEMENT FUNDAMENTALS - Basic Tools and Concepts in Operations Management - Tools for Managing Projects

7 important questions on OPERATIONS MANAGEMENT FUNDAMENTALS - Basic Tools and Concepts in Operations Management - Tools for Managing Projects

True or False. Design structure matrix (DSM) is also called dependency structure matrix.

True

True or False. Does a complex Design Structure Matrix may come with number values to indicate the strength of the relationships?

True

This diagram helps identify a project's critical path: all tasks that would extend the completion time of the whole project if delayed for even the smallest amount of time.

Activity-On-Node (AON) diagram
  • Higher grades + faster learning
  • Never study anything twice
  • 100% sure, 100% understanding
Discover Study Smart

True or False. Each node (AON) contains an activity label along with the amount of time (days) it takes to complete the activity.

True

True or False. Finding the critical path involves checking all the possible paths to identify the one with the longest duration.

True

True or False. A standard Gantt chart records the interdependencies between different tasks, providing enough information to determine the project's critical path.

False

True or False. The tools DSM, AON and Gantt Chart, can also be helpful for monitoring and refining processes.

True

The question on the page originate from the summary of the following study material:

  • A unique study and practice tool
  • Never study anything twice again
  • Get the grades you hope for
  • 100% sure, 100% understanding
Remember faster, study better. Scientifically proven.
Trustpilot Logo