A project manager need to calculate ______ to figure out how much flexibility the schedule has.

Slack

How to calculate Free Slack?

Subtract a task's earliest finish time (EF) from its successor's earliest start time (ES)

How to identify a critical path?

Look for the path with the longest total duration, or for the path whose tasks have zero total slack.