PROJECT MANAGEMENT - Project Scheduling and Execution - Managing Costs and Closing a Project

7 important questions on PROJECT MANAGEMENT - Project Scheduling and Execution - Managing Costs and Closing a Project

True or False. For computing estimated costs, do we include costs reserved for contingencies?

True. A budget cushion is needed if something goes wrong.

This is the amount of money the project team had "planned" on spending.

Planned Value

What is the formula for (SV) schedule variance?

Earned Value minus (-) Planned Value
  • Higher grades + faster learning
  • Never study anything twice
  • 100% sure, 100% understanding
Discover Study Smart

This value means that the project is underperforming: either over budget or behind schedule.

Negative Variance

True or False. The key to avoiding scope creep is to have an established change control system to approve or reject change requests.

True

Who decides whether the project deliverable meets the agreed "acceptance criteria", which means the project is complete, or, project closure?

Project Customer

This will show "how far ahead of or behind schedule" the project is.

Schedule Variance

The question on the page originate from the summary of the following study material:

  • A unique study and practice tool
  • Never study anything twice again
  • Get the grades you hope for
  • 100% sure, 100% understanding
Remember faster, study better. Scientifically proven.
Trustpilot Logo