4 important questions on PROJECT MANAGEMENT - Project Scheduling and Execution

What is the safest option if computing three point estimation?

Always round up

What is resource smoothing?

Shifts resources between tasks to minimize fluctuations in resource demands. It doesn't delay the project.

What is key to risk response? It lists who is responsible, at what point intervention becomes necessary to avoid or mitigate the risk, and what planned response is for each risk.

Risk Register
  • Higher grades + faster learning
  • Never study anything twice
  • 100% sure, 100% understanding
Discover Study Smart

What is a tool for planning responses to medium and high risks?

Risk Register

The question on the page originate from the summary of the following study material:

  • A unique study and practice tool
  • Never study anything twice again
  • Get the grades you hope for
  • 100% sure, 100% understanding
Remember faster, study better. Scientifically proven.
Trustpilot Logo