PROJECT MANAGEMENT - Project Scheduling and Execution - Estimating Task Duration and Deadlines
5 important questions on PROJECT MANAGEMENT - Project Scheduling and Execution - Estimating Task Duration and Deadlines
Using this technique, project managers use their findings to calculate a more precise estimate.
True or False. When getting the EF of a task with multiple predecessors, assign the highest number or the longest duration.
True or False. The latest finish (LF) of any given task is the latest start (LS) of its successor.
- Higher grades + faster learning
- Never study anything twice
- 100% sure, 100% understanding
True or False. A task without any successors signals the end of the project.
How to get LF if a task or two both feed into two successors?