PROJECT MANAGEMENT - Project Scheduling and Execution - Estimating Task Duration and Deadlines

5 important questions on PROJECT MANAGEMENT - Project Scheduling and Execution - Estimating Task Duration and Deadlines

Using this technique, project managers use their findings to calculate a more precise estimate.

Three Point Estimation

True or False. When getting the EF of a task with multiple predecessors, assign the highest number or the longest duration.

True

True or False. The latest finish (LF) of any given task is the latest start (LS) of its successor.

True
  • Higher grades + faster learning
  • Never study anything twice
  • 100% sure, 100% understanding
Discover Study Smart

True or False. A task without any successors signals the end of the project.

True

How to get LF if a task or two both feed into two successors?

Choose the earliest (shortest duration)

The question on the page originate from the summary of the following study material:

  • A unique study and practice tool
  • Never study anything twice again
  • Get the grades you hope for
  • 100% sure, 100% understanding
Remember faster, study better. Scientifically proven.
Trustpilot Logo