The Corrupting Influence of Variability - Cycle Time

3 important questions on The Corrupting Influence of Variability - Cycle Time

Assembly operations. What will be affected by increasing the following:

 

1. Number of components being assembled.

2.Variability of components arrivals.

3. Lack of coordination between component arrivals.

The performance of an assembly station is degraded.

What components make up CT?

  1. move time
  2. queue time
  3. setup time
  4. process time
  5. wait-to-batch time
  6. wait-in-batch time
  7. wait-to-match time

1: Can there be wait-to-batch or wait-in-batch time when there are no setups in the production process?

2: Can there be queue time when there are both process & transfer batches, or can there only be wait-in-batch and wait-to-batch times then?

1: Yes, but only for transfer batches.

 

2: I'm inclined to say: yes it can.
Although it might seem that queue time for batches is represented in wait-in-batch time, there could be a queue of batches. Queue time is also represented by the formulas in the 9.4.2 & 9.4.3 technical notes.

The question on the page originate from the summary of the following study material:

  • A unique study and practice tool
  • Never study anything twice again
  • Get the grades you hope for
  • 100% sure, 100% understanding
Remember faster, study better. Scientifically proven.
Trustpilot Logo