A Pull Planning Framework - Disaggregation
3 important questions on A Pull Planning Framework - Disaggregation
Which 3 planning horizons are typically used and what do they address?
Long term -> strategy
Intermediate term -> tactics
Short term -> control
Assign the right category (long, intermediate or short term) to the following subjects related to planning:
A: Preventive maintenance
B: Process control
C: Product designs
D: Facility locations
E: Staffing assignments
F: Worker assignments
Long term = 1, Intermediate term = 2, Short term =3
A: 2
B: 3
C: 1
D: 1
E: 2
F: 3
Apart from breaking down time in order to facilitate production planning and control, you can also break up the plant into which 3 more manageable pieces?
Processes, products & people.