Work authorisation and project control
3 important questions on Work authorisation and project control
Name the earned value definitions
- PV - Planned Value (budgeted cost of work scheduled)
- EV - Earned Value (budgeted cost of work performed or supposed cost)
- AC - Actual Cost (actual cost of work performed)
- SV - Schedule Variance (SV = EV - PV)
- TV - Time variance (SP - Status Date; SP is the date where PV - EV in time units)
- CV - Cost variance (CV = EV - AC)
- Positive variances imply good results
How do you calculate the Performance Index?
EV: earned value
PV: planned value
SPI > 1 (Ahead of schedule), SPI < 1 (Behind schedule)
How do you calculate the Cost Performance Index?
EV: earned value
AC: actual cost
CPI > 1 (Cost saving), CPI < 1 (Over expenditure)
The question on the page originate from the summary of the following study material:
- A unique study and practice tool
- Never study anything twice again
- Get the grades you hope for
- 100% sure, 100% understanding