MPC reference architecture framework - RCCP/Resource loading
7 important questions on MPC reference architecture framework - RCCP/Resource loading
In what is RCCP still flexible?
Rder acceptance (OA) and prduction planning are often functionally dispersed which means OA is not based on actual workload. What is the cause?
OA is often not based on actual workload what is the result?
- Overloaded system, no resource flexibility;
- Unrealistic due dates, no time flexibility;
- Higher grades + faster learning
- Never study anything twice
- 100% sure, 100% understanding
How can capacity violations be repaired? [6]
What is the downside?
- Shift jobs in time;
- Split jobs in two or more weeks;
- Increase order lead time
- decreasing start time;
- increasing completion time;
- Negotiate due date violation with customer;
- Expand resource capacity temporarily;
- Subcontract jobs or entire order;
Options are difficult to evaluate and/or costly and do not guarantee feasibility.
What is a hybrid approach considering RCCP?
What are RCCP uncertainties? [3]
- Processing times are stochastic;
- job occurerence may be uncertain;
- resource availability may be uncertain;
- etc.
What is does RCCP deal with?
The question on the page originate from the summary of the following study material:
- A unique study and practice tool
- Never study anything twice again
- Get the grades you hope for
- 100% sure, 100% understanding