Introducing Project Time Management - Defining the Project Timeline
14 important questions on Introducing Project Time Management - Defining the Project Timeline
What is the point of the project schedule?
What is the critical path used for?
- To consider which activities are critical
- To identify which activities have float/ slack
- To determine the earliest completion date of a project
What types of float are being recognized in a project?
- Free float - total time activity can be delayed without delaying start of a successor activity
- Total float- total time activity can be delayed without delaying project completion
- Negative total float - caused by constraints on activities
- Project float - the time the project can be delayed without passing the customer-expected completion date
- Higher grades + faster learning
- Never study anything twice
- 100% sure, 100% understanding
What is the difference between the critical path and critical chain method?
What is the key of CCM scheduling? When is this relevant?
What are means for resource leveling?
- changing timing of activities
- apply resources to critical path activities
- change project schedule (evenings, weekends, adding shifts)
- change resources, tools, equipment etc.
What do we mean with reverse resource allocation scheduling?
For which activities is resource smoothing value adding?
What is the trick with duration compression?
What are the two methods for activity duration compression?
- Crashing: adding more resources to the critical path activities, with a consequence of more costs
- Fast-tracking: changing the relationship of activities (e.g. paralleling rather than sequencing), with a consequence of more risk
What is the purpose of simulations?
- They allow the project manager to examine the feasibility of the project schedule under different conditions, variables, and events.
- They allow the project team to create responses to feasible situations, so that when the situation occurs the project team is ready
When is a project considered to be final?
What formats are recognized for a project schedule?
- Project Network Diagram
- Bar Charts
- Milestone Charts
- Schedule Baseline
- Schedule Data
What do we mean with updating the resource requirements?
The question on the page originate from the summary of the following study material:
- A unique study and practice tool
- Never study anything twice again
- Get the grades you hope for
- 100% sure, 100% understanding