Introducing Project Time Management - Creating the Schedule Management Plan

6 important questions on Introducing Project Time Management - Creating the Schedule Management Plan

What is included in the schedule management plan?

  • How the schedule will be created
  • The types of work to be completed
  • The resources and other attributes to predict when the work will be completed

What are two of the biggest factors in the creation of the schedule management plan process?

  • Organizational process assets
  • Enterprise Environmental Factors (can directly influence how the the schedule is planned and maintained, e.g. work hours etc.)

What is foundation for all the activities that a project manager undertakes to create a schedule?

The build of the schedule management plan
  • Higher grades + faster learning
  • Never study anything twice
  • 100% sure, 100% understanding
Discover Study Smart

What are two ways of creation of a schedule management plan?

  • Use organizational process assets and adapt a previous plan
  • Create a new plan and use certain tools and techniques: expert judgment, analytical techniques, meetings

What elements are defined in the schedule management plan?

  • The model for schedule development
  • Level of accuracy
  • Units of measure (days, hours, weeks)
  • Organizational Procedure Links
  • Control Thresholds - predefined variance of tasks
  • Rules of performance measurement - e.g. EVM
  • Reporting Formats
  • Process descriptions - which processes are addressed in this knowledge area

Define - schedule management plan

TBD

The question on the page originate from the summary of the following study material:

  • A unique study and practice tool
  • Never study anything twice again
  • Get the grades you hope for
  • 100% sure, 100% understanding
Remember faster, study better. Scientifically proven.
Trustpilot Logo