Scrum model assessment + quizzes

3 important questions on Scrum model assessment + quizzes

During a Sprint Review, the stakeholders notice that the product development progress is not very clearly visible and lacked transparency. Moreover, they are not able to understand the next steps. Who is responsible for this?
a) Development Team
b) Product Owner
c) Scrum Master
d) Scrum Team

Correct answer is ‘b’. Product Owner is responsible for maintaining the transparency of Product Backlog, the progress so far, and the next steps along with alternatives if any.

What are the true statements?
a) Scrum Team is responsible for formulating a Sprint Goal
b) When existing Product Backlog Items in the Sprint Backlog are modified, the Sprint Goal is bound to become invalid
c) The coherence between Product Backlog items is made transparent by Sprint Goal. Lack of coherence will lead to Development Team members working individually

Correct answers are ‘a’ and ‘c’. The Sprint Goal provides opportunity for team members to work together and offers some flexibility of adjusting the Product Backlog items when required. Development Team can modify the Product Backlog Items in the Sprint Backlog with Product Owner’s consent, such that the Sprint Goal will still be met.

For the first Sprint, the inputs are the Product Backlog and the Projected Capacity of the Development Team. What are the additional inputs to the subsequent Sprints?

a) Defect list from previous Sprint
b) Sprint Plan
c) Past performance of the Development Team
d) Latest Product Increment

Correct answers are ‘c’ and ‘d’.

The question on the page originate from the summary of the following study material:

  • A unique study and practice tool
  • Never study anything twice again
  • Get the grades you hope for
  • 100% sure, 100% understanding
Remember faster, study better. Scientifically proven.
Trustpilot Logo